A person pays Rs. 3000 to two workers for a task. If the first worker completes it in 4 days and the second in 6 days, how much does the faster worker get?
A. (a) Rs. 1200
B. (b) Rs. 1500
C. (c) Rs. 2000
D. (d) Rs. 1800
Explanation कार्यक्षमता का अनुपात = 1/4 : 1/6 = 3 : 2। तेज कर्मचारी (4 दिन वाला) का हिस्सा = (3/5) * 3000 = 1800 रुपये।